Vancouver, Canada
Flinders Resources Limited (“Flinders” or the “Company”) (TSXV: FDR) provides an update on the final stages of restarting graphite production at the Woxna mine and processing facility in central Sweden. Woxna is a fully permitted brownfields graphite mine, having been on care and maintenance since 2001. The plant restart was completed last month and operations commenced in July.
- Key progress milestones over the last month include:
- Wet commissioning of all systems completed;
- Feed Ore into mill and processing plant commenced;
- First graphite concentrate drawn from floatation circuit overflow;
- European customers conducting site visits;
- Vendor representatives on site to assist with fine tuning of new equipment;
- Invitations issued to key stakeholders for the formal opening ceremony of the Woxna facility in September
Blair Way, President and CEO, states,
“Our Woxna graphite plant is up and running in Sweden again, marking the culmination of our last 8 months of efforts. All is on track for full commissioning, with customers now coming to site to confirm our capabilities and discuss expanded supply contracts. Graphite production will place Flinders at the forefront of the graphite sector, with the ability to fill consumer needs immediately, and provide a sustainable European alternative to Chinese supply. Now that we have the confidence in our facility and product, we are working to expand our resource base through proving up our historical resources The September opening ceremony is a great opportunity to showcase our plant and capabilities to stakeholders.”
On behalf of the Board,
“Blair Way”
Blair Way, President and CEO
For more information contact:
Jim Powell +1 647-478-5806
info@flindersresources.com
Forward-Looking Information
Certain information in this news release may constitute forward-looking statements or forward-looking information within the meaning of applicable securities laws (collectively, “Forward-Looking Statements”). All statements, other than statements of historical fact that address activities, events or developments that the Company believes, expects or anticipates will or may occur in the future are Forward-Looking Statements. Forward-Looking Statements are often, but not always, identified by the use of words such as “seek,” “anticipate,” “believe,” “plan,” “estimate,” “expect,” and “intend” and statements that an event or result “may,” “will,” “can,” “should,” “could,” or “might” occur or be achieved and other similar expressions. Forward-Looking Statements are based upon the opinions and expectations of the Company based on information currently available to the Company. Forward-Looking Statements are subject to a number of factors, risks and uncertainties that may cause the actual results of the Company to differ materially from those discussed in the Forward-Looking Statements including, among other things, the Company has yet to generate a profit from its activities; there can be no guarantee that the estimates of quantities or qualities of minerals disclosed in the Company’s public record will be economically recoverable; uncertainties relating to the availability and costs of financing needed in the future; competition with other companies within the mining industry; the success of the Company is largely dependent upon the performance of its directors and officers and the Company’s ability to attract and train key personnel; changes in world metal markets and equity markets beyond the Company’s control; mineral reserves are, in the large part, estimates and no assurance can be given that the anticipated tonnages and grades will be achieved or that the indicated level of recovery will be realized; production rates and capital and other costs may vary significantly from estimates; the Company’s decision to restart production at the Woxna graphite project is based on historical production and the Company’s preliminary economic assessment (“PEA”) of the project and the Company has no plans to first complete a pre-feasibility or feasibility study on the project, as a result there is an increased risk of technical and economic failure for the Woxna graphite project; unexpected geological conditions; delays in obtaining or failure to obtain necessary permits and approvals from government authorities; all phases of a mining business present environmental and safety risks and hazards and are subject to environmental and safety regulation, and rehabilitation and restitution costs; the Company does not maintain insurance against environmental risks; and management of the Company have experience in mineral exploration but may lack all or some of the necessary technical training and experience to successfully develop and operate a mine. Although the Company believes that the expectations reflected in the Forward-Looking Statements, and the assumptions on which such Forward-Looking Statements are made, are reasonable, there can be no assurance that such expectations will prove to be correct. Readers are cautioned not to place undue reliance on Forward-Looking Statements, as there can be no assurance that the plans, intentions or expectations upon which the Forward-Looking Statements are based will occur. Forward-Looking Statements herein are made as at the date hereof, and unless otherwise required by law, the Company does not intend, or assume any obligation, to update these Forward-Looking Statements.
Preliminary Economic Assessment
The Company advises that it has not based its production decision on a feasibility study of mineral reserves, demonstrating economic and technical viability, and, as a result, there may be an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure. There is no guarantee that production will begin as anticipated or at all or that anticipated production costs will be achieved. Failure to commence production would have a material adverse impact on the Company’s ability to generate revenue and cash flow to fund operations. Failure to achieve the anticipated production costs would have a material adverse impact on the Company’s cash flow and future profitability.
The Company further cautions that the PEA is preliminary in nature. No mining study has been completed. Mineral resources are not mineral reserves and do not have demonstrated economic viability. There is no certainty that the PEA will be realized.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or the accuracy of this news release.